Slab base · Material planning
Gravel Under Concrete Slab Calculator
Estimate the gravel or crushed stone beneath your slab. Enter the base footprint and compacted depth, then use your supplier’s values to find loose cubic yards, US short tons and material cost.
Quick example: a 10 × 10 ft base at 4 inches compacted depth occupies 1.235 yd³. Your loose purchase quantity depends on the material’s volume adjustment and any handling allowance.
Your gravel base
Start with the finished, compacted layer.
10 × 10 ft at 4 in is an example, not a depth recommendation. Measure the whole base, including any extension beyond the slab. Use your project’s specified compacted depth.
Gravel order rules (optional)
Blank means no restriction. We round up to a multiple of the increment that also meets the minimum. Example: 1.56 yd³ needed with 0.5 yd³ increments means 2 yd³ ordered.
Add gravel pricing (optional)
USD. Blank fees count as $0. Cost uses the order quantity, including any entered minimum or increment.
Base quantity estimate
Compacted volume → loose volume → weight.
1 · Compacted base volume
33.333 ft³ in place. This is the finished layer, before a loose-volume adjustment.
2 · Loose volume needed
Needs supplier inputs
Enter your supplier’s loose-volume multiplier to estimate the amount to buy.
3 · Estimated delivery weight
Needs supplier inputs
First calculate loose volume, then add your supplier’s loose bulk density.
4 · Supplier order quantity
Needs supplier inputs
Enter the required supplier values and valid order rules.
5 · Materials + entered fees
Needs supplier inputs
A valid loose volume and price are needed.
Only entered minimums and increments are applied; blank rules mean no restriction. Confirm the billable quantity before ordering. Labor, equipment, taxes and unentered charges are excluded.
Keeps length and width only. Review the concrete footprint and thickness separately; its defaults are 4 in and 10% waste.
Two separate quantities
Measure the gravel layer, not the concrete
Use the length and width of the entire aggregate base. If your project calls for the base to extend beyond the concrete, include that extension in these dimensions.
Depth means the finished thickness after compaction. Keep the concrete slab thickness separate. A 4-inch concrete slab does not automatically require a 4-inch base.
For a rectangular layer, length × width × depth gives its volume. For an irregular footprint, divide it into non-overlapping rectangles, calculate each section, and add their volumes.
Use the Concrete Slab Calculator for the concrete above this layer, including bags versus ready-mix costs.
Concrete slab
Calculate concrete separately
Compacted aggregate base
This calculator measures this layer
Compacted quantities only
Gravel base volume for common slab sizes
These examples assume the base has exactly the listed footprint. They show finished compacted volume before a loose-volume multiplier or handling allowance. Depths compare quantities; they are not design recommendations.
| Base footprint | 4 in compacted | 6 in compacted |
|---|---|---|
| 10 × 10 ft | 1.235 yd³ | 1.852 yd³ |
| 12 × 12 ft | 1.778 yd³ | 2.667 yd³ |
| 20 × 20 ft | 4.938 yd³ | 7.407 yd³ |
Planning the concrete too? See concrete quantities for a 10×10 slab by thickness and bag size.
For a rectangular pad, the 10×12 slab guide compares a matching base with a 12×14 ft base extending 1 ft on each side.
How to calculate gravel under a slab
1. Find compacted volume
Compacted yd³ = length (ft) × width (ft) × depth (in) ÷ 324
Divide inches by 12 to get feet, then cubic feet by 27 to get cubic yards.
2. Convert to loose purchase volume
Loose yd³ = compacted yd³ × multiplier × (1 + handling % ÷ 100)
Use the supplier’s ratio of loose volume to compacted volume. Add handling only once.
3. Convert loose volume to weight
US short tons = loose yd³ × loose density (US short tons/yd³)
The density must describe the same loose material being purchased, not the compacted layer.
4. Apply order rules and your quote
Total = order quantity × price per unit + entered fees
Use matching units: loose cubic yards or US short tons. Apply the entered minimum, then round up to an increment multiple. Blank rules mean no restriction.
For example, 1.56 loose yd³ needed with a 0.5 yd³ sales increment becomes a 2 yd³ order: 0.44 yd³ above the calculated need. A 2.2 yd³ minimum with that increment becomes 2.5 yd³. These purchase rules do not change the finished base volume.
Worked example: 10 × 10 ft base, 4 inches compacted
Suppose your supplier gives a 1.20× loose-volume multiplier and 1.40 US short tons per loose yd³, and you add 5% handling. These are hypothetical inputs, not standard values for gravel.
1.235 compacted yd³ → 1.556 loose yd³ → 2.178 US short tons.
At an example $50 per US short ton plus $75 delivery, materials and fees total $183.89. The calculation uses unrounded quantities. Confirm the supplier’s actual billable quantity and quote.
What to ask before ordering gravel
- The exact product: confirm the aggregate type and grading specified for the base.
- Loose volume per compacted yard: ask how many delivered loose cubic yards are needed for one finished compacted cubic yard. Clarify whether their factor already includes handling losses.
- Loose bulk density: if buying by weight, request US short tons per loose cubic yard for that product and delivered moisture condition. Divide a density in lb/yd³ by 2,000 to get US short tons/yd³.
- The full quote: ask about billable quantity, minimum orders, delivery increments, truck access, delivery charges and taxes.
Do not enter a “95% compaction” requirement as a volume multiplier. A density-based compaction specification and the loose-to-compacted volume ratio are different measurements.
Gravel under concrete slab questions
How much gravel do I need under a 10x10 concrete slab?
For a base footprint of exactly 10 × 10 ft and a specified compacted depth of 4 inches, the finished layer occupies 33.33 cubic feet, or 1.235 cubic yards. That is compacted volume. To estimate loose material to purchase, multiply it by your supplier’s loose-volume factor and any separate handling allowance. The base footprint may be larger than the concrete slab.
How many tons of gravel do I need under a concrete slab?
Calculate the loose cubic yards first, then multiply by the supplier’s loose bulk density in US short tons per cubic yard. There is no single density built into this tool. Aggregate type, gradation and delivered condition affect the conversion. A US short ton is 2,000 lb; it is not a metric tonne or a British long ton.
Is the gravel depth the same as the concrete thickness?
No. The concrete slab and the aggregate base are separate layers. Enter the finished compacted depth specified for the base, not the slab thickness or the loose depth before compaction. The 4- and 6-inch examples on this page compare quantities only; they do not select a depth for your project.
Is a 1.20 multiplier the same as 20% compaction?
A 1.20 multiplier means you allow 1.20 loose cubic yards for every compacted cubic yard: 20% extra loose volume. If a supplier instead means that loose material loses 20% of its volume, the multiplier is 1 ÷ 0.80 = 1.25. Ask which definition they use. A specified percentage of maximum dry density is a different measure and cannot be entered as this volume multiplier.
Can I use gravel, crushed stone or crusher run in this calculator?
You can estimate the geometric volume of a specified aggregate layer with this tool. Use the product’s own loose-volume factor and loose bulk density for purchase estimates. The calculator does not decide which aggregate is suitable; confirm the specified material, grading and base preparation for your slab before ordering.
Does gravel replace a vapor retarder under an indoor slab?
No. An aggregate layer and a vapor retarder perform different functions. NRMCA CIP 29 explains that even a coarse-stone capillary break does not stop moisture vapor transmission. Follow the project’s moisture-control details; this quantity calculator does not design that assembly.
Does this include gravel delivery and installation?
The optional cost estimate uses the order quantity at your entered price plus delivery or other fees. Enter the supplier’s minimum order and sales increment to adjust the purchase quantity; blank rules apply no restriction. The calculator does not automatically include installation, equipment, taxes or unentered charges. Ask for the actual billable quantity and full quote before buying.
Calculation basis & references
Geometric volume uses 12 inches per foot and 27 cubic feet per cubic yard. Loose-volume multipliers, densities and prices come from your inputs; the calculator does not assume a universal gravel conversion.
Vulcan Materials’ aggregate estimating tools provide a supplier reference for quantity planning. Vulcan recommends reviewing estimates and product availability with a local representative.
NRMCA CIP 29: Vapor Retarders Under Slabs on Grade (PDF) explains why base support and moisture control need separate consideration. An aggregate layer does not replace a specified vapor retarder.
Updated November 16, 2026. This tool estimates material quantities; base design and installation requirements come from your project specification.